Under the state’s current Stay-at-Home Order, Algonquin Road is experiencing reduced traffic volumes. Due to this unique scenario, the project[...]
Blog
Project Update 5/6/2020
RECENT WORK COMPLETED: Randall Road: Storm sewer installation is complete from Bunker Hill Dr. to Stonegate Rd. Algonquin Road: Concrete[...]
Project Update 4/27/2020
Work completed last week: Algonquin Road: Various small pavement and driveway pours occurred. Randall Road: Preparation for mainline pavement pours[...]
Driveway Entrance Opening/Closure Update
Concrete pavement and curb continues to be installed on Algonquin and Randall Roads. To allow for this installation, some driveway[...]
Permanent Concrete Pavement Placed on Algonquin Rd.
Last week provided some very noticeable project changes! On Thursday April 2nd, two lanes of permanent concrete pavement were[...]
Improvement Work to Resume on Algonquin Road
Beginning next week, work on Algonquin Rd. south side lanes will begin in earnest. In preparation for final grading, starting[...]
Project Progress Video
Much of the work on a roadway project can go unseen. Check out the most recent drone video showing the[...]
Traffic Movement Restrictions at the Intersection of Randall Road and Stonegate Road
New traffic movement restrictions will be put in place at the intersection of Randall Road and Stonegate Road. Beginning January[...]
Project Update 12/17/2019
Work continues on the Randall Road Improvements. Storm Sewer Storm sewer installation is complete on Randall Rd. from Acorn Ln./Polaris[...]
Project Update 11/26/2019
Pavement removal work is taking place on Randall Road from Bunker Hill Drive to the south. This work will continue[...]