Current project information.

The project is approximately 29% complete.

 

Miller Rd. Now Open

Randall Road Project Update

Update – Week of 4/13/2026 Construction activities will ramp up this week including work on the new roadway and the Woods Creek Bridge: Dirt operations will resume with excavation from the north being moved to the south Continued work on the Woods Creek bridge deck forming Continued installation and backfilling[...]

READ MORE

Randall Road Project Update

Update – Week of 4/06/2026 Construction activities will focus on the area north and south of the Woods Creek Bridge and may include: Installation of the new Woods Creek bridge beams Continued installation and backfilling of retaining walls Ongoing construction of the bridge structure Installation of creek bed stabilization Continued[...]

READ MORE