Current project information.

The project is approximately 26% complete.

 

Miller Rd. Now Open

Randall Road Project Update

Update – Week of 3/2/2026 Crews will be working as weather permits. Work will focus on the Woods Creek Bridge and may include: Continued installation of retaining walls Ongoing construction of the bridge structure Traffic: Expect frequent southbound lane closures at the bridge while crews work, with only one southbound[...]

READ MORE

Randall Road Project Update

Update – Week of 2/23/2026 Crews will be working as weather permits. Work will focus on the Woods Creek Bridge and may include: Continued installation of retaining walls Ongoing construction of the bridge structure Traffic: Expect frequent southbound lane closures at the bridge while crews work, with only one southbound[...]

READ MORE