Last week, all lanes on Randall Road were opened to travel! Thank you for your patience! The improvement project is[...]
Blog
Randall Road Project Update – Lanes Open
Beginning Wednesday, August 25th (weather dependent), all lanes on Randall Road and Algonquin Road will be open with the exception[...]
Randall Road Project Update 08/06/2021
Pavement Marking Update: Good News! The contractor has received shipment of the permanent pavement marking tape. Preparations for the installation[...]
Randall Road Project Update 7/20/2021
Pavement Marking Process Update: The permanent striping is a highly reflective inlaid tape that is placed in the grooves of[...]
Randall Road Project Update 6/23/2021
Work completed last week: The Randall Road medians are complete and landscaping is finished in various locations. The pedestrian tunnel lighting[...]
Randall Road Project Alert: Intermittent Lane Closures Week of 6/14/2021
The final surface course is scheduled to be paved at the following locations during the week of 6/14/2021. Anticipate various[...]
Randall Road Project Update 6/4/2021
After the staging of the northbound traffic to the outside northbound lanes, the contractor began completing the remaining left-turn lanes,[...]
Randall Road Project Update 5/17/2021
The project is now 85% complete. On THURSDAY, MAY 6th, the northbound Randall Road traffic was shifted onto the two[...]
Union Pacific Railroad Crossing Closure W/Detour directing traffic along Randall/Algonquin Roads
Please be advised that on Wednesday, May 12th, there may be increased traffic on both Algonquin Road and Randall Road. [...]
Randall Road Project Update 4/29/2021
The project is now 82% complete. The electricians continue to work on the northbound street lighting and various traffic signals. [...]