On Wednesday, September 2nd all Randall Road traffic will be shifted to the new pavement between Bunker Hill Dr. and[...]
Update
Several lane closures and a traffic shift scheduled for next week on Randall Road
Several lane closures and a traffic shift are scheduled for next week on Randall Road. Monday, August 31st : A[...]
Project Update 8/26/2020
Work last week: Randall Rd: Completed the poured-in-place end of the pedestrian underpass. Continued forming and pouring the walls leading[...]
Project Update 8/17/2020
Work last week Randall Rd: Earth excavation from Bunker Hill Dr. to Harnish Dr. was completed and stone base installation[...]
Project Update 7/31/2020
Work completed last week Randall Rd: Asphalt placement continued at various locations including driveways Miscellaneous concrete pours occurred for driveways[...]
Project Update – 07/16/2020
Work Last Week: Randall Rd: Installed asphalt driveways, widening and pavement at Polaris and Commercial Dr. Excavated Huntington Rd to[...]
Project Update – 07/09/2020
Work last week: Preparation for the concrete pavement turn lanes and intersections on Randall Rd. from Algonquin Rd. to Bunker[...]
Project Update – 6/26/2020
Last week the contractor continued to make great progress on the rebuilding of Randall and Algonquin Roads. Randall Road: 4[...]
Project Update – Algonquin Road Legal Width Restriction
Algonquin Road construction staging currently limits traffic to a single lane heading east and a single lane heading west with[...]
Project Update 6/16/2020
Project Work Completed Last Week: Randall Rd from Algonquin Rd to Bunker Hill was prepared for concrete placement Excavation and[...]