Project Update 8/17/2020

Work last week Randall Rd: Earth excavation from Bunker Hill Dr. to Harnish Dr. was completed and stone base installation was started. Storm sewer installation for the south bound lanes has been completed. Excavation for and placement of the remaining pedestrian underpass was completed last week, work has started on the poured in place “mouth”… Continue reading

More

Project Update 7/31/2020

Work completed last week Randall Rd: Asphalt placement continued at various locations including driveways Miscellaneous concrete pours occurred for driveways and turn lanes Huntington Dr., Bunker Hill Dr. and Polaris Dr. excavated and storm sewer and stone placed Pavement removal was completed in the southbound lanes from Bunker Hill Dr. to Harnish Dr. and storm… Continue reading

More

Project Update – 07/16/2020

Work Last Week: Randall Rd: Installed asphalt driveways, widening and pavement at Polaris and Commercial Dr. Excavated Huntington Rd to grade and placed stone base Asphalt placement occurred on Polaris Dr. and Commercial Dr. Asphalt entrances were also installed Street light installation continued along Randall Rd. Work continued on the southbound retaining wall and the… Continue reading

More

Project Update – 07/09/2020

Work last week: Preparation for the concrete pavement turn lanes and intersections on Randall Rd. from Algonquin Rd. to Bunker Hill Dr. was ongoing. Work on the retaining wall continued.  Installation of the street lighting conduits/foundations/poles continued.  Prep work for the installation of the second half of the pedestrian tunnel is underway with the tunnel… Continue reading

More

Project Update – 6/26/2020

Last week the contractor continued to make great progress on the rebuilding of Randall and Algonquin Roads. Randall Road: 4 concrete lanes were poured for southbound Randall Rd. from Algonquin Rd to Bunker Hill Dr.  Traffic pattern changes occurred on Polaris Dr. and Crystal Lake Rd. to allow the removal of existing pavement and work… Continue reading