Project Update – 10/20/2020

Work completed last week: Randall Rd – southbound traffic was moved onto the new pavement from Bunker Hill to Harnish while northbound traffic remained on the existing roadway Earth excavation, stone base placement and grading from Stonegate to the north project limits (north of Acorn) was completed and prepared for concrete pavement placement. 2 of… Continue reading

More

Randall Lane Shift

During the week of 10/12/20 southbound Randall Road traffic will be shifted to the new pavement from Bunker Hill to Harnish. Northbound traffic will remain in the current location for approximately 1 week to allow intersection work at Bunker Hill/Huntington. There will be intermittent lane closures throughout the day when the switch occurs to implement… Continue reading

More

Project Update – 10/02/2020

Work completed last week: Randall Rd Concrete temporary pavement placement for the remainder of section south of Bunker Hill Dr. was completed Worked on sidewalk preparation/placement and landscaping between Bunker Hill Dr. and Algonquin Rd. Continued pavement removal on the east side of Randall Rd from the project north limit to Stonegate Rd. Installed traffic… Continue reading

More

Project Update 09/18/2020

Work completed last week: Randall Rd Concrete pavement placement for the turn lanes south of Bunker Hill Dr. was completed Curb and gutter placed south of Bunker Hill Dr. Completed sidewalk placement and landscaping between Bunker Hill Dr. and Algonquin Rd. Implemented placing traffic onto the new pavement from Bunker Hill Dr. to the north… Continue reading

More

Overnight Pavement Milling to Occur on Randall Rd.

Pavement milling will be taking place on Randall Road during the following times: Thursday 9/3 to Friday 9/4: 7:00pm – 4:00am Friday 9/4 to Saturday 9/5: 7:00pm – 4:00am The milling will take place in the blocked off construction area away from the moving vehicles and should have minimal impact on traffic.   Please watch… Continue reading

More