Project Update 6/10/2020

Project Work Completed Last Week: Temporary pavement was placed at the intersection of Algonquin Rd and Randall Rd to allow traffic to use the newly poured lanes Curb and gutter was poured on the north leg of Randall Rd, as well as concrete driveways in the same area Work started on the south bound Randall… Continue reading

More

New lane configuration – Algonquin Rd.

CLICK HERE to check out this video showing the new lane configuration starting later this week on Algonquin Road.

More

Algonquin Road Lane Reconfiguration – Beginning the week of June 1st

Under the state’s current Stay-at-Home Order, Algonquin Road is experiencing reduced traffic volumes.  Due to this unique scenario, the project team is aiming to fast-track the remaining underground work along the north side of Algonquin Rd. To facilitate this, beginning the week of June 1st, traffic on Algonquin Rd. will be shifted to the new… Continue reading

More

Project Update 5/6/2020

RECENT WORK COMPLETED: Randall Road: Storm sewer installation is complete from Bunker Hill Dr. to Stonegate Rd.  Algonquin Road: Concrete installation is complete on the south leg of the Algonquin Rd./Crystal Lake Rd. intersection.  The intersection has reopened to traffic.  CLICK HERE to see photos. WORK PLANNED FOR WEEK OF 5/11/2020: Randall Road: A large… Continue reading

More

Project Update 4/27/2020

Work completed last week: Algonquin Road: Various small pavement and driveway pours occurred. Randall Road: Preparation for mainline pavement pours continued. At Stonegate Rd. – bases were installed for the new street lighting. Work planned for this week: Algonquin Road: Pavement and driveway pours will continue along Algonquin Rd.  At Algonquin Rd. and Crystal Lake… Continue reading

More