Project Update 12/15/2020

Work completed last week: Randall Road: Poured miscellaneous curb, gutter and sidewalk gaps Completed storm sewer on Acorn Lane Filled in intersection pavement panels on Acorn and at drives Placed topsoil, grass seed and erosion control blanket Completed pouring all sections of the sidewalk and crash wall on the north bound retaining wall Installed lighting… Continue reading

More

Project Update – 11/23/2020

Work completed last week: Randall Road: Switched eastbound leg of Acorn to allow for construction in the center of the road Excavated and placed stone base for the northbound lanes from Harnish to Huntington Poured concrete pavement infill panels at southeast corner of Algonquin and Randall Poured northbound pavement from Acorn to the north limits,… Continue reading

More

Algonquin Lane Shift

Lane Shift on Eastbound Algonquin Road: On Thursday, 11/05 Eastbound Algonquin Road traffic will be shifted to the inside lane approaching Randall Road to allow the remaining concrete pavement placement work to occur at Randall. 

More

Project Update – 11/02/2020

Work completed last week: Check out this 30 day Glimpse into lane expansion work on Randall CLICK HERE. Randall Road: Switched northbound Randall Road to the new pavement from Harnish to Huntington/Bunker Hill. Poured two new additional northbound concrete pavement lanes from Stonegate to Polaris, providing four travel lanes for the future roadway Completed concrete… Continue reading

More

Algonquin Lane Shift

Westbound Algonquin Road traffic is scheduled to be shifted to the new pavement on the north side of the road on Monday, 10/26, weather dependent. This shift will allow for two lanes of traffic heading westbound on Algonquin going forward. There will be intermittent lane closures throughout the day when the switch occurs to implement… Continue reading

More