Lane closures starting 5/29/2019

AT&T utility work will require a lane closure on eastbound Algonquin Road, west of the Randall/Algonquin intersection.  This work will begin Wednesday 5/29 and likely last through the week.  Southbound Randall Road, from north of Acorn Lane to Algonquin Road, will also have daily lane closures for utility work as Com Ed continues the relocation… Continue reading

More

Lane closures on Randall Road 5/22 through 5/24

Lanes will be reduced to 1 lane in each direction on Randall Road today through Friday for the installation of storm sewer across Randall Road north of Acorn Lane.  Reductions will occur between the hours of 7 am and 5 pm.  Please plan accordingly.

More

Project Update 5/16/2019

Excavation and stone placement for the temporary pavement continues along the east side of Randall Road. Excavation for the northbound retaining wall continues between Harnish Drive and Huntington Drive. Storm sewer installation has begun as well.  Next week, earth excavation and stone placement will continue, and storm sewer installation and piling installation at the retaining… Continue reading

More

Project Update 5/8/2019

Excavation and stone placement for the temporary pavement continues along the east side of Randall Road. Work has begun on the northbound retaining wall between Harnish Drive and Huntington Drive. Temporary street lighting installation is ongoing. In the next week, storm sewer installation and piling installation at the retaining wall will begin.  All work is… Continue reading

More

Project Update 5/1/2019

Inclement weather has slowed progress a bit this past week.  When the weather cooperates, the contractor will continue with the earth excavation, utility relocation, and temporary lighting installation. Please drive carefully through the construction zone.

More