Overall Project Construction Progress 100%

Randall Road Schedule

2019 2019 2020 2020 2021 2021
Task Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec
Detention pond work

·

Construct retaining wall - eastside

·

Install storm sewer - eastside

·

Install pedestrian underpass eastside

·

Shift traffic to the east

·

Randall Road - Winter Shutdown - Stage I - Southbound lanes

2019 2019 2020 2020 2021 2021
Task Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec
Construct retaining wall - westside

·

Install storm sewer - westside

·

·

Install pedestrian underpass - westside

·

Pavement removal

·

Construct southbound permanent pavement and curb & gutter

·

Construct temporary pavement for Stage II

·

Install permanent lighting - westside

·

Install permanent landscaping - westside

·

Shift traffic to westside on new pavement

·

Randall Road - Winter Shutdown - Stage II - Northbound lanes

2019 2019 2020 2020 2021 2021
Task Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec
Complete detention ponds

·

Storm sewer

·

Pavement removal

·

Construct northbound permanent pavement and curb & gutter

·

Construct temporary pavement for Stage III

·

Begin permanent traffic signal install

·

Permanent lighting - eastside

·

Permanent landscaping - eastside

·

Shift traffic to outsides of Randall on new pavement

·

Randall Road - Winter Shutdown - Stage III - Center lanes

2019 2019 2020 2020 2021 2021
Task Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec
Remove temporary pavement 

·

Complete storm sewer

·

Construct permament pavement and medians

·

Complete traffic signal installation

·

Complete lighting installation

·

Complete permanent landscaping 

·

Install permanent pavement striping

·

Open Roadway June 30, 2021

Algonquin Road Schedule

2019 2019 2020 2020 2021 2021
Task Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec
Install temporary drainage

·

Install temporary pavement 

·

Install storm sewer - northside

·

Algonquin Road - Winter Shutdown - Stage I - Eastbound lanes

2019 2019 2020 2020 2021 2021
Task Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec
Shift traffic to westbound lanes

·

Install storm sewer - southside

·

Pavement removal 

·

Construct eastbound pavement and curb & gutter

·

·

Install permanent lighting - southside

·

Install permanent landscaping - southside

·

Algonquin Road - Winter Shutdown - Stage II - Westbound lanes

2019 2019 2020 2020 2021 2021
Task Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec
Shift traffic to eastbound lanes

·

Install storm sewer - northside

·

Pavement removal 

·

Construct westbound pavement and curb & gutter

·

Install permanent Lighting - northside

·

Install permanent landscaping - northside

·

Algonquin Road - Winter Shutdown - Stage III - Center lanes

2019 2019 2020 2020 2021 2021
Task Jan - June July - Dec Jan - June July - Dec Jan - June July - Dec
Remove temporary pavement 

·

Complete storm sewer

·

Construct permament pavement and medians

·

Complete traffic signal installation

·

Complete lighting installation

·

Complete permanent landscaping 

·

Install permanent pavement striping

·

Open Roadway June 30, 2021

* Schedule Subject to Change