Randall Road Schedule
2019 | 2019 | 2020 | 2020 | 2021 | 2021 | |
Task | Jan - June | July - Dec | Jan - June | July - Dec | Jan - June | July - Dec |
Detention pond work |
· |
|||||
Construct retaining wall - eastside |
· |
|||||
Install storm sewer - eastside |
· |
|||||
Install pedestrian underpass eastside |
· |
|||||
Shift traffic to the east |
· |
Randall Road - Winter Shutdown - Stage I - Southbound lanes
2019 | 2019 | 2020 | 2020 | 2021 | 2021 | |
Task | Jan - June | July - Dec | Jan - June | July - Dec | Jan - June | July - Dec |
Construct retaining wall - westside |
· |
|||||
Install storm sewer - westside |
· |
· |
||||
Install pedestrian underpass - westside |
· |
|||||
Pavement removal |
· |
|||||
Construct southbound permanent pavement and curb & gutter |
· |
|||||
Construct temporary pavement for Stage II |
· |
|||||
Install permanent lighting - westside |
· |
|||||
Install permanent landscaping - westside |
· |
|||||
Shift traffic to westside on new pavement |
· |
Randall Road - Winter Shutdown - Stage II - Northbound lanes
2019 | 2019 | 2020 | 2020 | 2021 | 2021 | |
Task | Jan - June | July - Dec | Jan - June | July - Dec | Jan - June | July - Dec |
Complete detention ponds |
· |
|||||
Storm sewer |
· |
|||||
Pavement removal |
· |
|||||
Construct northbound permanent pavement and curb & gutter |
· |
|||||
Construct temporary pavement for Stage III |
· |
|||||
Begin permanent traffic signal install |
· |
|||||
Permanent lighting - eastside |
· |
|||||
Permanent landscaping - eastside |
· |
|||||
Shift traffic to outsides of Randall on new pavement |
· |
Randall Road - Winter Shutdown - Stage III - Center lanes
2019 | 2019 | 2020 | 2020 | 2021 | 2021 | |
Task | Jan - June | July - Dec | Jan - June | July - Dec | Jan - June | July - Dec |
Remove temporary pavement |
· |
|||||
Complete storm sewer |
· |
|||||
Construct permament pavement and medians |
· |
|||||
Complete traffic signal installation |
· |
|||||
Complete lighting installation |
· |
|||||
Complete permanent landscaping |
· |
|||||
Install permanent pavement striping |
· |
|||||
Open Roadway | June 30, 2021 |
Algonquin Road Schedule
2019 | 2019 | 2020 | 2020 | 2021 | 2021 | |
Task | Jan - June | July - Dec | Jan - June | July - Dec | Jan - June | July - Dec |
Install temporary drainage |
· |
|||||
Install temporary pavement |
· |
|||||
Install storm sewer - northside |
· |
Algonquin Road - Winter Shutdown - Stage I - Eastbound lanes
2019 | 2019 | 2020 | 2020 | 2021 | 2021 | |
Task | Jan - June | July - Dec | Jan - June | July - Dec | Jan - June | July - Dec |
Shift traffic to westbound lanes |
· |
|||||
Install storm sewer - southside |
· |
|||||
Pavement removal |
· |
|||||
Construct eastbound pavement and curb & gutter |
· |
· |
||||
Install permanent lighting - southside |
· |
|||||
Install permanent landscaping - southside |
· |
Algonquin Road - Winter Shutdown - Stage II - Westbound lanes
2019 | 2019 | 2020 | 2020 | 2021 | 2021 | |
Task | Jan - June | July - Dec | Jan - June | July - Dec | Jan - June | July - Dec |
Shift traffic to eastbound lanes |
· |
|||||
Install storm sewer - northside |
· |
|||||
Pavement removal |
· |
|||||
Construct westbound pavement and curb & gutter |
· |
|||||
Install permanent Lighting - northside |
· |
|||||
Install permanent landscaping - northside |
· |
Algonquin Road - Winter Shutdown - Stage III - Center lanes
2019 | 2019 | 2020 | 2020 | 2021 | 2021 | |
Task | Jan - June | July - Dec | Jan - June | July - Dec | Jan - June | July - Dec |
Remove temporary pavement |
· |
|||||
Complete storm sewer |
· |
|||||
Construct permament pavement and medians |
· |
|||||
Complete traffic signal installation |
· |
|||||
Complete lighting installation |
· |
|||||
Complete permanent landscaping |
· |
|||||
Install permanent pavement striping |
· |
|||||
Open Roadway | June 30, 2021 |
* Schedule Subject to Change