Project Update 12/03/2018 – Lane Closures

Starting Wednesday, December 5th,  there will be lane closures between approximately 7:00am and 4:00pm on Randall Rd. just north of Algonquin Rd. These closures are to facilitate increasing the left turn lane length when headed southbound on Randall Rd. and turning eastbound onto Algonquin Rd. This increase should allow those turning eastbound onto Algonquin Rd.… Continue reading

More

Project Update 11/19/2018

Tuesday, November 20th, traffic will be staged from Huntington/Bunker Hill Dr. to Harnish Drive.  Northbound and Southbound lanes will be shifted to the West to create a work zone for the installation of the pedestrian underpass and retaining wall.   Following the traffic staging, a temporary concrete barrier wall will be installed to separate motorists from… Continue reading

More

Project Update 11/12/2018

The temporary traffic signals at Bunker Hill/Huntington and Randall Road, as well as the temporary traffic signal at Algonquin and Randall Road will be activated tomorrow, Tuesday, November 13.  These installations will replace the permanently mounted traffic signals allowing the intersection to be fully functional while construction is ongoing.  The temporary installation allows the lanes,… Continue reading

More

Project Update 10/29/2018

Tomorrow, October 30th, minor traffic staging will take place in the southbound lanes of Randall Road south of Bunker Hill Drive/N. Huntington Drive. Traffic will be shifted east to allow removal of the existing shoulder and replacement with temporary pavement in anticipation of pedestrian underpass and retaining wall construction. Lane closures will occur during this… Continue reading

More

Project Update 10/10/2018

Work continues on the installation of temporary traffic signals and temporary lighting. Nicor is in the process of relocating existing utilities along the north side of Algonquin Road near Crystal Lake Rd. Com Ed is tentatively scheduled to start relocation work the week of 10/22. Work zone speed limit signs have been installed, reducing speeds… Continue reading

More

Scheduled Project Work for Week of 9/24/2018

Beginning the week of September 24, 2018, installation of temporary traffic signals and temporary lighting will begin at various intersections.  This ongoing work will continue for the next month as crews prepare to remove the existing systems to allow the staging of traffic for reconstruction.  Most work will be completed behind the curb, but periodic… Continue reading

More

Utility Relocations to Start Week of 9/3/2018

Beginning the week of September 3rd, 2018, Commonwealth Edison will begin utility relocations at Harnish and Randall Road.  The work will occur along the east side of the road (northbound lanes), and continue to the north towards Huntington Drive. Traffic disruptions should be minimal as the work is contained off of the pavement in the… Continue reading

More

Project Update 08/27/2018

NICOR, ComEd and ATT utility relocations are scheduled to begin in mid-September, continuing through the winter and into spring of 2019. The County and construction company representatives have been meeting to coordinate the roadway construction schedule with the planned utility relocations. The construction company is getting ready to begin the following; median removals, pre-stage temporary… Continue reading

More

Utility Relocation to Start July/August

Utility relocation work (ComEd, Nicor, AT&T) to start July/August.

More