Monday, October 7th, traffic is scheduled to shift to new temporary pavement on the east side of Randall Road between[...]
Blog
Project Update 9/25/2019
Storm Sewer and Water Main Work Scheduled – Underground storm sewer and water main work is scheduled to begin this[...]
Project Update 9/6/2019
Concrete Crushing Complete – The concrete crushing is complete and screening of the asphalt grindings continues to remove oversized materials.[...]
Project Update 8/19/2019
Traffic Shift/Pavement Removal Complete Traffic has been shifted to the new temporary pavement on the east side of Randall Road. [...]
Commercial entrance closures/Maps showing alternate routes
Several business entrances along the west side of Randall Road are now temporarily closed following the lane shift to the[...]
Traffic lane shifting delayed until Tuesday 7/30 due to weather
Good morning – Please be advised that the traffic lane shifting on Randall scheduled for today has been delayed until[...]
Traffic Lane Shifting Scheduled for Monday 7/29
Traffic will be shifting to new temporary pavement on the east side of Randall Road on Monday, July 29th. Please[...]
Project Update 7/26/2019
Retaining wall construction work continues between Harnish Drive and Huntington Drive. Pavement removal continues on the south side of[...]
Project Update 7/18
Algonquin Road traffic has been shifted north to newly installed temporary pavement so work can begin on the south side[...]
Project Update 7/8/2019
Temporary pavement installation is complete on the north side of Algonquin Road. Beginning Tuesday July 9th, traffic will be shifted[...]