Work continues on the Randall Road Improvements. Storm Sewer Storm sewer installation is complete on Randall Rd. from Acorn Ln./Polaris[...]
Update
Project Update 11/26/2019
Pavement removal work is taking place on Randall Road from Bunker Hill Drive to the south. This work will continue[...]
Project Update 11/15/2019
Project work continues despite Mother Nature’s best efforts! Storm Sewer Work Storm sewer work is complete on Algonquin Road Storm[...]
Project Update10/28/2019
Storm Sewer and Water Main Work Underway- Storm sewer work along Randall Road is scheduled to begin this week starting[...]
Traffic Lane Shifting Scheduled for Monday 10/7
Monday, October 7th, traffic is scheduled to shift to new temporary pavement on the east side of Randall Road between[...]
Project Update 9/25/2019
Storm Sewer and Water Main Work Scheduled – Underground storm sewer and water main work is scheduled to begin this[...]
Project Update 9/6/2019
Concrete Crushing Complete – The concrete crushing is complete and screening of the asphalt grindings continues to remove oversized materials.[...]
Project Update 8/19/2019
Traffic Shift/Pavement Removal Complete Traffic has been shifted to the new temporary pavement on the east side of Randall Road. [...]
Commercial entrance closures/Maps showing alternate routes
Several business entrances along the west side of Randall Road are now temporarily closed following the lane shift to the[...]
Traffic lane shifting delayed until Tuesday 7/30 due to weather
Good morning – Please be advised that the traffic lane shifting on Randall scheduled for today has been delayed until[...]