Storm Sewer and Water Main Work Scheduled – 
Underground storm sewer and water main work is scheduled to begin this week.

Pedestrian Tunnel Work is Ongoing – 
Construction work on the pedestrian tunnel continues. Work on the retaining walls adjacent to the tunnel will follow.

Temporary Pavement Installation – 
Temporary pavement is scheduled to be installed on Randall Rd. between Harnish Dr. and Huntington Dr. this week.  Once the temporary pavement installation is complete, traffic will be shifted to the east onto the temporary pavement so that construction work can occur on the west side of Randall Rd.  CLICK HERE to watch a short video about temporary pavement.

Please drive carefully through the construction zone. 

Comments are disabled