Project Update 8/17/2020

Work last week Randall Rd: Earth excavation from Bunker Hill Dr. to Harnish Dr. was completed and stone base installation was started. Storm sewer installation for the south bound lanes has been completed. Excavation for and placement of the remaining pedestrian underpass was completed last week, work has started on the poured in place “mouth”… Continue reading

More

Project Update 7/31/2020

Work completed last week Randall Rd: Asphalt placement continued at various locations including driveways Miscellaneous concrete pours occurred for driveways and turn lanes Huntington Dr., Bunker Hill Dr. and Polaris Dr. excavated and storm sewer and stone placed Pavement removal was completed in the southbound lanes from Bunker Hill Dr. to Harnish Dr. and storm… Continue reading

More

Project Update – 07/16/2020

Work Last Week: Randall Rd: Installed asphalt driveways, widening and pavement at Polaris and Commercial Dr. Excavated Huntington Rd to grade and placed stone base Asphalt placement occurred on Polaris Dr. and Commercial Dr. Asphalt entrances were also installed Street light installation continued along Randall Rd. Work continued on the southbound retaining wall and the… Continue reading

More

Project Update – 07/09/2020

Work last week: Preparation for the concrete pavement turn lanes and intersections on Randall Rd. from Algonquin Rd. to Bunker Hill Dr. was ongoing. Work on the retaining wall continued.  Installation of the street lighting conduits/foundations/poles continued.  Prep work for the installation of the second half of the pedestrian tunnel is underway with the tunnel… Continue reading

More

Project Update – 6/26/2020

Last week the contractor continued to make great progress on the rebuilding of Randall and Algonquin Roads. Randall Road: 4 concrete lanes were poured for southbound Randall Rd. from Algonquin Rd to Bunker Hill Dr.  Traffic pattern changes occurred on Polaris Dr. and Crystal Lake Rd. to allow the removal of existing pavement and work… Continue reading

More

Project Update – Algonquin Road Legal Width Restriction

Algonquin Road construction staging currently limits traffic to a single lane heading east and a single lane heading west with a left turn lane in each direction at the side streets, Randall/Algonquin intersection, and Butera entrance. While under this staging, vehicles traveling on Algonquin Rd. through the construction zone will be restricted to the legal… Continue reading

More

Project Update 6/16/2020

Project Work Completed Last Week: Randall Rd from Algonquin Rd to Bunker Hill was prepared for concrete placement Excavation and pile driving at the south bound retaining wall on Randall Rd. is complete Permanent street lighting was installed and activated on the south side of Algonquin Rd Pavement removal was started on the north side… Continue reading

More

Project Update 6/10/2020

Project Work Completed Last Week: Temporary pavement was placed at the intersection of Algonquin Rd and Randall Rd to allow traffic to use the newly poured lanes Curb and gutter was poured on the north leg of Randall Rd, as well as concrete driveways in the same area Work started on the south bound Randall… Continue reading

More

New lane configuration – Algonquin Rd.

CLICK HERE to check out this video showing the new lane configuration starting later this week on Algonquin Road.

More

Algonquin Road Lane Reconfiguration – Beginning the week of June 1st

Under the state’s current Stay-at-Home Order, Algonquin Road is experiencing reduced traffic volumes.  Due to this unique scenario, the project team is aiming to fast-track the remaining underground work along the north side of Algonquin Rd. To facilitate this, beginning the week of June 1st, traffic on Algonquin Rd. will be shifted to the new… Continue reading

More