Scheduled Project Work for Week of 9/24/2018

Beginning the week of September 24, 2018, installation of temporary traffic signals and temporary lighting will begin at various intersections.  This ongoing work will continue for the next month as crews prepare to remove the existing systems to allow the staging of traffic for reconstruction.  Most work will be completed behind the curb, but periodic… Continue reading

More

Utility Relocations to Start Week of 9/3/2018

Beginning the week of September 3rd, 2018, Commonwealth Edison will begin utility relocations at Harnish and Randall Road.  The work will occur along the east side of the road (northbound lanes), and continue to the north towards Huntington Drive. Traffic disruptions should be minimal as the work is contained off of the pavement in the… Continue reading

More

Project Update 08/27/2018

NICOR, ComEd and ATT utility relocations are scheduled to begin in mid-September, continuing through the winter and into spring of 2019. The County and construction company representatives have been meeting to coordinate the roadway construction schedule with the planned utility relocations. The construction company is getting ready to begin the following; median removals, pre-stage temporary… Continue reading

More

Utility Relocation to Start July/August

Utility relocation work (ComEd, Nicor, AT&T) to start July/August.

More