Project Update 8/19/2019

Traffic Shift/Pavement Removal Complete Traffic has been shifted to the new temporary pavement on the east side of Randall Road.  On the west side of Randall Road, removal of existing pavement is complete. Pavement Milling Video CLICK HERE. Concrete Crushing to Occur The mobile concrete crusher will be onsite this week to recycle the concrete… Continue reading

More

Commercial entrance closures/Maps showing alternate routes

Several business entrances along the west side of Randall Road are now temporarily closed following the lane shift to the east. These closures are necessary for traffic to travel safely through the area and to allow construction to continue to move forward.  ALL BUSINESSES ARE OPEN and can still be easily accessed through the next… Continue reading

More

Traffic lane shifting delayed until Tuesday 7/30 due to weather

Good morning – Please be advised that the traffic lane shifting on Randall scheduled for today has been delayed until tomorrow due to rain. Thank you!

More

Traffic Lane Shifting Scheduled for Monday 7/29

Traffic will be shifting to new temporary pavement on the east side of Randall Road on Monday, July 29th.  Please be aware of this upcoming traffic pattern change and drive carefully through the new lane configuration.

More

Project Update 7/26/2019

Retaining wall construction work continues between Harnish Drive and Huntington Drive.   Pavement removal continues on the south side of Algonquin Road and storm sewer installation will begin this week once pavement removal is completed. Work to build the temporary pavement is completed along the east side of Randall Road.  Traffic will be shifting to… Continue reading

More

Project Update 7/18

Algonquin Road traffic has been shifted north to newly installed temporary pavement so work can begin on the south side of the road. You are still able to access local area businesses. Work to build the temporary pavement continues along the east side of Randall Road.  CLICK HERE to watch a slideshow of the work. … Continue reading

More

Project Update 7/8/2019

Temporary pavement installation is complete on the north side of Algonquin Road.  Beginning Tuesday July 9th, traffic will be shifted to the newly installed pavement so work can begin on the south side of Algonquin Road. Access to area businesses will be maintained at all times. Work to build the temporary pavement continues along the… Continue reading

More

Project Update 6/27/2019

Work to build the temporary pavement continues along the east side of Randall Road. CLICK HERE to see concrete being poured for the temporary pavement.  The driveway access located between the Taco Bell and Steak ‘n Shake off of Randall Road will be closed through approximately Friday, June 28th for temporary pavement installation.  Access to… Continue reading

More

Driveway Access Closure 6/24-6/28

The driveway access located between the Taco Bell and Steak ‘n Shake off of Randall Road will be closed Monday, June 24th through Friday, June 28th for temporary concrete pavement installation. Access to the adjoining businesses is available at the commercial entrance directly to the north and via Acorn Ln.  Thank you for your patience… Continue reading

More

Project Update 6/14/2019

Excavation and stone placement for the temporary pavement continues along the east side of Randall Road. Temporary pavement installation is scheduled to begin next week. Huntington Drive and Acorn Lane will be widened in conjunction with the temporary pavement placement on Randall Rd to allow traffic to continue in its current patterns on these side… Continue reading

More