Project Update 09/18/2020

Work completed last week: Randall Rd Concrete pavement placement for the turn lanes south of Bunker Hill Dr. was completed Curb and gutter placed south of Bunker Hill Dr. Completed sidewalk placement and landscaping between Bunker Hill Dr. and Algonquin Rd. Implemented placing traffic onto the new pavement from Bunker Hill Dr. to the north… Continue reading

More

Overnight Pavement Milling to Occur on Randall Rd.

Pavement milling will be taking place on Randall Road during the following times: Thursday 9/3 to Friday 9/4: 7:00pm – 4:00am Friday 9/4 to Saturday 9/5: 7:00pm – 4:00am The milling will take place in the blocked off construction area away from the moving vehicles and should have minimal impact on traffic.   Please watch… Continue reading

More

Commercial Business Entrances to Open on Randall

Beginning on September 2nd, several commercial business entrances will be opened along the westside of Randall Rd.  CLICK HERE TO VIEW BUSINESS ENTRANCES OPENING SOUTH OF ALGONQUIN CLICK HERE TO VIEW BUSINESS ENTRANCES OPENING NORTH OF ALGONQUIN

More

Randall Lane Shift Visualization Video

On Wednesday, September 2nd  all Randall Road traffic will be shifted to the new pavement between Bunker Hill Dr. and Stonegate Rd. and will remain on the new pavement to the north limits of the project.  There will be intermittent lane closures throughout the day to implement the switch. CLICK HERE TO WATCH A VIDEO… Continue reading

More

Several lane closures and a traffic shift scheduled for next week on Randall Road

Several lane closures and a traffic shift are scheduled for next week on Randall Road. Monday, August 31st : A daytime southbound lane closure will occur on Randall Rd. for hot mix asphalt work between Stonegate Rd. and Bunker Hill Dr. Tuesday morning, September 1st through Wednesday morning September 2nd (including overnight): A southbound lane… Continue reading

More

Project Update 8/26/2020

Work last week: Randall Rd:  Completed the poured-in-place end of the pedestrian underpass. Continued forming and pouring the walls leading to the west side of the underpass. CLICK HERE to watch a quick Sneak Peek video of the Pedestrian Underpass. Graded the stone base from Bunker Hill Dr. to Harnish Dr. for preparation of concrete… Continue reading

More

Project Update 8/17/2020

Work last week Randall Rd: Earth excavation from Bunker Hill Dr. to Harnish Dr. was completed and stone base installation was started. Storm sewer installation for the south bound lanes has been completed. Excavation for and placement of the remaining pedestrian underpass was completed last week, work has started on the poured in place “mouth”… Continue reading

More

Project Update 7/31/2020

Work completed last week Randall Rd: Asphalt placement continued at various locations including driveways Miscellaneous concrete pours occurred for driveways and turn lanes Huntington Dr., Bunker Hill Dr. and Polaris Dr. excavated and storm sewer and stone placed Pavement removal was completed in the southbound lanes from Bunker Hill Dr. to Harnish Dr. and storm… Continue reading

More

Project Update – 07/16/2020

Work Last Week: Randall Rd: Installed asphalt driveways, widening and pavement at Polaris and Commercial Dr. Excavated Huntington Rd to grade and placed stone base Asphalt placement occurred on Polaris Dr. and Commercial Dr. Asphalt entrances were also installed Street light installation continued along Randall Rd. Work continued on the southbound retaining wall and the… Continue reading

More

Project Update – 07/09/2020

Work last week: Preparation for the concrete pavement turn lanes and intersections on Randall Rd. from Algonquin Rd. to Bunker Hill Dr. was ongoing. Work on the retaining wall continued.  Installation of the street lighting conduits/foundations/poles continued.  Prep work for the installation of the second half of the pedestrian tunnel is underway with the tunnel… Continue reading

More