Project Update 5/16/2019

Excavation and stone placement for the temporary pavement continues along the east side of Randall Road. Excavation for the northbound retaining wall continues between Harnish Drive and Huntington Drive. Storm sewer installation has begun as well.  Next week, earth excavation and stone placement will continue, and storm sewer installation and piling installation at the retaining… Continue reading

More

Project Update 5/8/2019

Excavation and stone placement for the temporary pavement continues along the east side of Randall Road. Work has begun on the northbound retaining wall between Harnish Drive and Huntington Drive. Temporary street lighting installation is ongoing. In the next week, storm sewer installation and piling installation at the retaining wall will begin.  All work is… Continue reading

More

Project Update 5/1/2019

Inclement weather has slowed progress a bit this past week.  When the weather cooperates, the contractor will continue with the earth excavation, utility relocation, and temporary lighting installation. Please drive carefully through the construction zone.

More

Project Update 04/23/2019

Earth excavation continues on the east side of Randall Road in preparation for temporary pavement installation. Utility relocation and temporary lighting installation is ongoing as well.  Pothole patching is scheduled to take place later this week. Please drive carefully through the construction zone. CLICK HERE to visit the Photo webpage to see work in progress.

More

Project Update 4/16/2019

Earth excavation continues on the east side of Randall Road in preparation for temporary pavement installation. Utility relocation and temporary lighting installation is ongoing as well.  Pothole patching is scheduled to take place later this week. Please drive carefully through the construction zone.

More

Project Update 4/10/2019

Active construction is kicking into gear.  Earth excavation has begun on the east side of Randall Road in preparation for temporary pavement installation.  Please stay alert for trucks entering and leaving the area, pay attention to flaggers for directions, and drive carefully through the construction zone.

More

Project Update 4/1/2019

Beginning Tuesday, April 2, 2019, a traffic pattern shift will occur on Randall Road.  Existing medians on Randall Road were removed and temporary pavement has been placed in these areas to allow traffic to be shifted and the construction work to continue. Watch for new traffic patterns. Please proceed with caution through the work zone… Continue reading

More

Project Update 3/12/2019 – Lane Closures

Beginning Thursday, March 14, 2019, daily lane closures will occur as the contractor begins work to remove existing medians on Randall Road and Algonquin Road.  This will allow the placement of temporary pavement for traffic to be shifted as the roadway is widened. Please proceed with caution through the work zone and watch for workers… Continue reading

More

Project Update 2/12/2019

ComEd, Nicor, and ATT utility relocation continues. Tree and brush removal has occurred where the pedestrian path will be installed between Randall Rd. and Stonegate Rd. Tree and brush removal continues along the east side of Randall Rd., north of Harnish Dr. to Huntington Dr.  Once this area is cleared of trees and brush, the… Continue reading

More

Project Update 1/15/2019

Tree and brush removal continues along the east side of Randall Rd., north of Harnish Dr. to Huntington Dr.  Once the area is cleared of trees and brush, the contractor will begin excavation to get ready for the new retaining wall installation. Utility relocation will continue with Com Ed working along Algonquin Rd., Nicor working… Continue reading

More