Upcoming Stonegate Road Closure

Beginning Monday, 4/12 (weather permitting), Stonegate Road will be under construction near the Randall Road intersection to mill the existing pavement, complete the cement base stabilization, and install the new asphalt pavement.  During this time, Stonegate Road will be open to Local Traffic Only.  Flaggers will be present during the day while work is being… Continue reading

More

Randall Road Project Update 3/24/2021

The project is now 79% complete. The electricians continued to work through the winter when they were able to and have made a lot of progress on the project.  The permanent signals have been installed and many of the street lights are up as well. These won’t be able to be activated until we shift… Continue reading

More

Randall Road Project Update 3/24/2021 – Signal Controller Cabinet Work

On Monday, March 22nd, 2021, the controller for the traffic signals at Randall Road and Miller Road was successfully changed out. Impact to traffic was minimal and the work went smoothly. Thank you to everyone who patiently used the intersection. On Wednesday, March 24th, 2021, the same operation will occur at Randall Road and Harnish… Continue reading

More

Project Update 3/19/2021 – Signal Controller Cabinet Installation

Randall Road Improvements Construction Alert – The contractor will be replacing traffic signal controller cabinets at several intersections during the next few weeks. To complete this work, the signals will need to be turned off for a period of time between approximately 9:00 am and 1:00 pm, and the intersection will become a 4-way stop.… Continue reading

More

Traffic Signal Installations

With warmer weather upon us, electricians have been working to install permanent traffic signal poles and signal heads throughout the Randall Road Improvement Project. These signals will be activated at a later date and the temporary signals will be removed at that time. This installation work should have minimal impact on traffic flow. CLICK HERE… Continue reading

More

Project Update 12/15/2020

Work completed last week: Randall Road: Poured miscellaneous curb, gutter and sidewalk gaps Completed storm sewer on Acorn Lane Filled in intersection pavement panels on Acorn and at drives Placed topsoil, grass seed and erosion control blanket Completed pouring all sections of the sidewalk and crash wall on the north bound retaining wall Installed lighting… Continue reading

More

Project Update – 11/23/2020

Work completed last week: Randall Road: Switched eastbound leg of Acorn to allow for construction in the center of the road Excavated and placed stone base for the northbound lanes from Harnish to Huntington Poured concrete pavement infill panels at southeast corner of Algonquin and Randall Poured northbound pavement from Acorn to the north limits,… Continue reading

More

Algonquin Lane Shift

Lane Shift on Eastbound Algonquin Road: On Thursday, 11/05 Eastbound Algonquin Road traffic will be shifted to the inside lane approaching Randall Road to allow the remaining concrete pavement placement work to occur at Randall. 

More

Project Update – 11/02/2020

Work completed last week: Check out this 30 day Glimpse into lane expansion work on Randall CLICK HERE. Randall Road: Switched northbound Randall Road to the new pavement from Harnish to Huntington/Bunker Hill. Poured two new additional northbound concrete pavement lanes from Stonegate to Polaris, providing four travel lanes for the future roadway Completed concrete… Continue reading

More

Algonquin Lane Shift

Westbound Algonquin Road traffic is scheduled to be shifted to the new pavement on the north side of the road on Monday, 10/26, weather dependent. This shift will allow for two lanes of traffic heading westbound on Algonquin going forward. There will be intermittent lane closures throughout the day when the switch occurs to implement… Continue reading

More