Project Update – 6/26/2020

Last week the contractor continued to make great progress on the rebuilding of Randall and Algonquin Roads. Randall Road: 4 concrete lanes were poured for southbound Randall Rd. from Algonquin Rd to Bunker Hill Dr.  Traffic pattern changes occurred on Polaris Dr. and Crystal Lake Rd. to allow the removal of existing pavement and work… Continue reading

More

Project Update – Algonquin Road Legal Width Restriction

Algonquin Road construction staging currently limits traffic to a single lane heading east and a single lane heading west with a left turn lane in each direction at the side streets, Randall/Algonquin intersection, and Butera entrance. While under this staging, vehicles traveling on Algonquin Rd. through the construction zone will be restricted to the legal… Continue reading

More

Project Update 6/16/2020

Project Work Completed Last Week: Randall Rd from Algonquin Rd to Bunker Hill was prepared for concrete placement Excavation and pile driving at the south bound retaining wall on Randall Rd. is complete Permanent street lighting was installed and activated on the south side of Algonquin Rd Pavement removal was started on the north side… Continue reading

More

Project Update 6/10/2020

Project Work Completed Last Week: Temporary pavement was placed at the intersection of Algonquin Rd and Randall Rd to allow traffic to use the newly poured lanes Curb and gutter was poured on the north leg of Randall Rd, as well as concrete driveways in the same area Work started on the south bound Randall… Continue reading

More

New lane configuration – Algonquin Rd.

CLICK HERE to check out this video showing the new lane configuration starting later this week on Algonquin Road.

More

Algonquin Road Lane Reconfiguration – Beginning the week of June 1st

Under the state’s current Stay-at-Home Order, Algonquin Road is experiencing reduced traffic volumes.  Due to this unique scenario, the project team is aiming to fast-track the remaining underground work along the north side of Algonquin Rd. To facilitate this, beginning the week of June 1st, traffic on Algonquin Rd. will be shifted to the new… Continue reading

More

Project Update 5/6/2020

RECENT WORK COMPLETED: Randall Road: Storm sewer installation is complete from Bunker Hill Dr. to Stonegate Rd.  Algonquin Road: Concrete installation is complete on the south leg of the Algonquin Rd./Crystal Lake Rd. intersection.  The intersection has reopened to traffic.  CLICK HERE to see photos. WORK PLANNED FOR WEEK OF 5/11/2020: Randall Road: A large… Continue reading

More

Project Update 4/27/2020

Work completed last week: Algonquin Road: Various small pavement and driveway pours occurred. Randall Road: Preparation for mainline pavement pours continued. At Stonegate Rd. – bases were installed for the new street lighting. Work planned for this week: Algonquin Road: Pavement and driveway pours will continue along Algonquin Rd.  At Algonquin Rd. and Crystal Lake… Continue reading

More

Driveway Entrance Opening/Closure Update

Concrete pavement and curb continues to be installed on Algonquin and Randall Roads. To allow for this installation, some driveway entrances may be temporarily closed. Please use nearby entrances for alternative access. Tentative schedule below:   Algonquin Road Friday 4/17 – The 3 closed driveway entrances east of Randall will reopen (the Butera driveway to… Continue reading

More

Permanent Concrete Pavement Placed on Algonquin Rd.

Last week provided some very noticeable project changes!    On Thursday April 2nd, two lanes of permanent concrete pavement were placed on Algonquin Road from Talaga Drive to Crystal Lake Road.   CLICK HERE to see video of the pavement work in action.  CLICK HERE to see photos. This week, the contractor is working on… Continue reading

More