Project Update 3/12/2019 – Lane Closures

Beginning Thursday, March 14, 2019, daily lane closures will occur as the contractor begins work to remove existing medians on Randall Road and Algonquin Road.  This will allow the placement of temporary pavement for traffic to be shifted as the roadway is widened. Please proceed with caution through the work zone and watch for workers… Continue reading

More

Project Update 2/12/2019

ComEd, Nicor, and ATT utility relocation continues. Tree and brush removal has occurred where the pedestrian path will be installed between Randall Rd. and Stonegate Rd. Tree and brush removal continues along the east side of Randall Rd., north of Harnish Dr. to Huntington Dr.  Once this area is cleared of trees and brush, the… Continue reading

More

Project Update 1/15/2019

Tree and brush removal continues along the east side of Randall Rd., north of Harnish Dr. to Huntington Dr.  Once the area is cleared of trees and brush, the contractor will begin excavation to get ready for the new retaining wall installation. Utility relocation will continue with Com Ed working along Algonquin Rd., Nicor working… Continue reading

More

Project Update 12/21/2018

Happy Holidays!  Utility work will resume after the New Year.  Construction on the retaining wall located north of Harnish Drive on the east side of Randall Road is scheduled to start in January. As always, please travel through the work zone with caution.

More

Project Update 12/03/2018 – Lane Closures

Starting Wednesday, December 5th,  there will be lane closures between approximately 7:00am and 4:00pm on Randall Rd. just north of Algonquin Rd. These closures are to facilitate increasing the left turn lane length when headed southbound on Randall Rd. and turning eastbound onto Algonquin Rd. This increase should allow those turning eastbound onto Algonquin Rd.… Continue reading

More

Project Update 11/19/2018

Tuesday, November 20th, traffic will be staged from Huntington/Bunker Hill Dr. to Harnish Drive.  Northbound and Southbound lanes will be shifted to the West to create a work zone for the installation of the pedestrian underpass and retaining wall.   Following the traffic staging, a temporary concrete barrier wall will be installed to separate motorists from… Continue reading

More

Project Update 11/12/2018

The temporary traffic signals at Bunker Hill/Huntington and Randall Road, as well as the temporary traffic signal at Algonquin and Randall Road will be activated tomorrow, Tuesday, November 13.  These installations will replace the permanently mounted traffic signals allowing the intersection to be fully functional while construction is ongoing.  The temporary installation allows the lanes,… Continue reading

More

Project Update 10/29/2018

Tomorrow, October 30th, minor traffic staging will take place in the southbound lanes of Randall Road south of Bunker Hill Drive/N. Huntington Drive. Traffic will be shifted east to allow removal of the existing shoulder and replacement with temporary pavement in anticipation of pedestrian underpass and retaining wall construction. Lane closures will occur during this… Continue reading

More

Project Update 10/10/2018

Work continues on the installation of temporary traffic signals and temporary lighting. Nicor is in the process of relocating existing utilities along the north side of Algonquin Road near Crystal Lake Rd. Com Ed is tentatively scheduled to start relocation work the week of 10/22. Work zone speed limit signs have been installed, reducing speeds… Continue reading

More

Scheduled Project Work for Week of 9/24/2018

Beginning the week of September 24, 2018, installation of temporary traffic signals and temporary lighting will begin at various intersections.  This ongoing work will continue for the next month as crews prepare to remove the existing systems to allow the staging of traffic for reconstruction.  Most work will be completed behind the curb, but periodic… Continue reading

More