Project Update 5/6/2020

RECENT WORK COMPLETED: Randall Road: Storm sewer installation is complete from Bunker Hill Dr. to Stonegate Rd.  Algonquin Road: Concrete installation is complete on the south leg of the Algonquin Rd./Crystal Lake Rd. intersection.  The intersection has reopened to traffic.  CLICK HERE to see photos. WORK PLANNED FOR WEEK OF 5/11/2020: Randall Road: A large… Continue reading

More

Project Update 4/27/2020

Work completed last week: Algonquin Road: Various small pavement and driveway pours occurred. Randall Road: Preparation for mainline pavement pours continued. At Stonegate Rd. – bases were installed for the new street lighting. Work planned for this week: Algonquin Road: Pavement and driveway pours will continue along Algonquin Rd.  At Algonquin Rd. and Crystal Lake… Continue reading

More

Driveway Entrance Opening/Closure Update

Concrete pavement and curb continues to be installed on Algonquin and Randall Roads. To allow for this installation, some driveway entrances may be temporarily closed. Please use nearby entrances for alternative access. Tentative schedule below:   Algonquin Road Friday 4/17 – The 3 closed driveway entrances east of Randall will reopen (the Butera driveway to… Continue reading

More

Permanent Concrete Pavement Placed on Algonquin Rd.

Last week provided some very noticeable project changes!    On Thursday April 2nd, two lanes of permanent concrete pavement were placed on Algonquin Road from Talaga Drive to Crystal Lake Road.   CLICK HERE to see video of the pavement work in action.  CLICK HERE to see photos. This week, the contractor is working on… Continue reading

More

Improvement Work to Resume on Algonquin Road

Beginning next week, work on Algonquin Rd. south side lanes will begin in earnest. In preparation for final grading, starting on Monday, March 30th, temporary asphalt surfaces will be removed from driveway entrances located along the south side of Algonquin Rd.  Final grading and prep work will continue throughout next week with a target date… Continue reading

More

Project Progress Video

Much of the work on a roadway project can go unseen. Check out the most recent drone video showing the project progress on Randall Road this past year.  CLICK HERE.

More

Traffic Movement Restrictions at the Intersection of Randall Road and Stonegate Road

New traffic movement restrictions will be put in place at the intersection of Randall Road and Stonegate Road.  Beginning January 9th, 2020, left turns and through movements will NOT BE ALLOWED from Stonegate Road onto or across Randall Road.  Motorists will still be able to make right turn movements onto Randall Road from Stonegate Road.… Continue reading

More

Project Update 12/17/2019

Work continues on the Randall Road Improvements. Storm Sewer Storm sewer installation is complete on Randall Rd. from Acorn Ln./Polaris Dr. to Bunker Hill Dr./Huntington Dr.  Remaining storm sewer installation on Randall Rd. from Bunker Hill Dr./Huntington Dr. to Harnish Dr. will resume in the spring.  Pavement Eastbound Algonquin Rd. from Harvest Gate to Crystal… Continue reading

More

Project Update 11/26/2019

Pavement removal work is taking place on Randall Road from Bunker Hill Drive to the south.  This work will continue tomorrow and Monday 12/2.  Watch for truck traffic.  Storm sewer will be crossing Bunker Hill Drive along the west side of Randall Road on Monday, 12/2 thru Wednesday, December 12/4. Please watch for flaggers at… Continue reading

More

Project Update 11/15/2019

Project work continues despite Mother Nature’s best efforts! Storm Sewer Work Storm sewer work is complete on Algonquin Road  Storm sewer work along Randall Road is complete from Acorn/Polaris to Algonquin Road Storm sewer work is ongoing on Randall Road south of Algonquin Road  Pedestrian Tunnel Work  Construction work on the pedestrian tunnel and adjacent… Continue reading

More