Project Progress Video

Much of the work on a roadway project can go unseen. Check out the most recent drone video showing the project progress on Randall Road this past year.  CLICK HERE.

More

Traffic Movement Restrictions at the Intersection of Randall Road and Stonegate Road

New traffic movement restrictions will be put in place at the intersection of Randall Road and Stonegate Road.  Beginning January 9th, 2020, left turns and through movements will NOT BE ALLOWED from Stonegate Road onto or across Randall Road.  Motorists will still be able to make right turn movements onto Randall Road from Stonegate Road.… Continue reading

More

Project Update 12/17/2019

Work continues on the Randall Road Improvements. Storm Sewer Storm sewer installation is complete on Randall Rd. from Acorn Ln./Polaris Dr. to Bunker Hill Dr./Huntington Dr.  Remaining storm sewer installation on Randall Rd. from Bunker Hill Dr./Huntington Dr. to Harnish Dr. will resume in the spring.  Pavement Eastbound Algonquin Rd. from Harvest Gate to Crystal… Continue reading

More

Project Update 11/26/2019

Pavement removal work is taking place on Randall Road from Bunker Hill Drive to the south.  This work will continue tomorrow and Monday 12/2.  Watch for truck traffic.  Storm sewer will be crossing Bunker Hill Drive along the west side of Randall Road on Monday, 12/2 thru Wednesday, December 12/4. Please watch for flaggers at… Continue reading

More

Project Update 11/15/2019

Project work continues despite Mother Nature’s best efforts! Storm Sewer Work Storm sewer work is complete on Algonquin Road  Storm sewer work along Randall Road is complete from Acorn/Polaris to Algonquin Road Storm sewer work is ongoing on Randall Road south of Algonquin Road  Pedestrian Tunnel Work  Construction work on the pedestrian tunnel and adjacent… Continue reading

More

Project Update10/28/2019

Storm Sewer and Water Main Work Underway- Storm sewer work along Randall Road is scheduled to begin this week starting near Acorn Lane and progressing south.  Water main work is complete on Algonquin Road west of Randall Rd. Storm sewer work continues on Algonquin Rd. Pedestrian Tunnel Work is Ongoing –  Construction work on the… Continue reading

More

Traffic Lane Shifting Scheduled for Monday 10/7

Monday, October 7th, traffic is scheduled to shift to new temporary pavement on the east side of Randall Road between Harnish Drive and Huntington/Bunker Hill Drive so construction work can occur on the west side of Randall Road. Please be aware of this upcoming traffic pattern change and drive carefully through the new lane configuration.

More

Project Update 9/25/2019

Storm Sewer and Water Main Work Scheduled –  Underground storm sewer and water main work is scheduled to begin this week. Pedestrian Tunnel Work is Ongoing –  Construction work on the pedestrian tunnel continues. Work on the retaining walls adjacent to the tunnel will follow. Temporary Pavement Installation –  Temporary pavement is scheduled to be installed… Continue reading

More

Project Update 9/6/2019

Concrete Crushing Complete – The concrete crushing is complete and screening of the asphalt grindings continues to remove oversized materials. The recycled concrete and asphalt pavement will be incorporated into the stone base for the new roadway. Northbound Retaining Wall Work is Complete –  Northbound retaining wall construction is complete between Harnish Drive and Huntington… Continue reading

More

Project Update 8/19/2019

Traffic Shift/Pavement Removal Complete Traffic has been shifted to the new temporary pavement on the east side of Randall Road.  On the west side of Randall Road, removal of existing pavement is complete. Pavement Milling Video CLICK HERE. Concrete Crushing to Occur The mobile concrete crusher will be onsite this week to recycle the concrete… Continue reading

More