Algonquin Lane Shift

Westbound Algonquin Road traffic is scheduled to be shifted to the new pavement on the north side of the road on Monday, 10/26, weather dependent. This shift will allow for two lanes of traffic heading westbound on Algonquin going forward. There will be intermittent lane closures throughout the day when the switch occurs to implement… Continue reading

More

Project Update – 10/20/2020

Work completed last week: Randall Rd – southbound traffic was moved onto the new pavement from Bunker Hill to Harnish while northbound traffic remained on the existing roadway Earth excavation, stone base placement and grading from Stonegate to the north project limits (north of Acorn) was completed and prepared for concrete pavement placement. 2 of… Continue reading

More

Randall Lane Shift

During the week of 10/12/20 southbound Randall Road traffic will be shifted to the new pavement from Bunker Hill to Harnish. Northbound traffic will remain in the current location for approximately 1 week to allow intersection work at Bunker Hill/Huntington. There will be intermittent lane closures throughout the day when the switch occurs to implement… Continue reading

More

Project Update – 10/02/2020

Work completed last week: Randall Rd Concrete temporary pavement placement for the remainder of section south of Bunker Hill Dr. was completed Worked on sidewalk preparation/placement and landscaping between Bunker Hill Dr. and Algonquin Rd. Continued pavement removal on the east side of Randall Rd from the project north limit to Stonegate Rd. Installed traffic… Continue reading

More

Project Update 09/18/2020

Work completed last week: Randall Rd Concrete pavement placement for the turn lanes south of Bunker Hill Dr. was completed Curb and gutter placed south of Bunker Hill Dr. Completed sidewalk placement and landscaping between Bunker Hill Dr. and Algonquin Rd. Implemented placing traffic onto the new pavement from Bunker Hill Dr. to the north… Continue reading

More

Overnight Pavement Milling to Occur on Randall Rd.

Pavement milling will be taking place on Randall Road during the following times: Thursday 9/3 to Friday 9/4: 7:00pm – 4:00am Friday 9/4 to Saturday 9/5: 7:00pm – 4:00am The milling will take place in the blocked off construction area away from the moving vehicles and should have minimal impact on traffic.   Please watch… Continue reading

More

Commercial Business Entrances to Open on Randall

Beginning on September 2nd, several commercial business entrances will be opened along the westside of Randall Rd.  CLICK HERE TO VIEW BUSINESS ENTRANCES OPENING SOUTH OF ALGONQUIN CLICK HERE TO VIEW BUSINESS ENTRANCES OPENING NORTH OF ALGONQUIN

More

Randall Lane Shift Visualization Video

On Wednesday, September 2nd  all Randall Road traffic will be shifted to the new pavement between Bunker Hill Dr. and Stonegate Rd. and will remain on the new pavement to the north limits of the project.  There will be intermittent lane closures throughout the day to implement the switch. CLICK HERE TO WATCH A VIDEO… Continue reading

More

Several lane closures and a traffic shift scheduled for next week on Randall Road

Several lane closures and a traffic shift are scheduled for next week on Randall Road. Monday, August 31st : A daytime southbound lane closure will occur on Randall Rd. for hot mix asphalt work between Stonegate Rd. and Bunker Hill Dr. Tuesday morning, September 1st through Wednesday morning September 2nd (including overnight): A southbound lane… Continue reading

More

Project Update 8/26/2020

Work last week: Randall Rd:  Completed the poured-in-place end of the pedestrian underpass. Continued forming and pouring the walls leading to the west side of the underpass. CLICK HERE to watch a quick Sneak Peek video of the Pedestrian Underpass. Graded the stone base from Bunker Hill Dr. to Harnish Dr. for preparation of concrete… Continue reading

More