Project Update – Algonquin Road Legal Width Restriction

Algonquin Road construction staging currently limits traffic to a single lane heading east and a single lane heading west with a left turn lane in each direction at the side streets, Randall/Algonquin intersection, and Butera entrance. While under this staging, vehicles traveling on Algonquin Rd. through the construction zone will be restricted to the legal… Continue reading

More

Project Update 6/16/2020

Project Work Completed Last Week: Randall Rd from Algonquin Rd to Bunker Hill was prepared for concrete placement Excavation and pile driving at the south bound retaining wall on Randall Rd. is complete Permanent street lighting was installed and activated on the south side of Algonquin Rd Pavement removal was started on the north side… Continue reading

More

Project Update 6/10/2020

Project Work Completed Last Week: Temporary pavement was placed at the intersection of Algonquin Rd and Randall Rd to allow traffic to use the newly poured lanes Curb and gutter was poured on the north leg of Randall Rd, as well as concrete driveways in the same area Work started on the south bound Randall… Continue reading

More

New lane configuration – Algonquin Rd.

CLICK HERE to check out this video showing the new lane configuration starting later this week on Algonquin Road.

More

Algonquin Road Lane Reconfiguration – Beginning the week of June 1st

Under the state‚Äôs current Stay-at-Home Order, Algonquin Road is experiencing reduced traffic volumes.  Due to this unique scenario, the project team is aiming to fast-track the remaining underground work along the north side of Algonquin Rd. To facilitate this, beginning the week of June 1st, traffic on Algonquin Rd. will be shifted to the new… Continue reading

More