Current project information.

The project is approximately 16% complete.

 

Click to view the Detour Video and learn details.

Project Update: Miller Road Bridge Progress

Work on the Miller Road Bridge and Randall Road intersection is progressing. The project team will be taking advantage of an opportunity to temporarily lift the detour restriction and reopen Miller Road at Randall Road in early December, pending weather. Temporary pavement will be built to transition between the existing[...]

READ MORE

Randall Road Project Update

The week of 10/27/2025, scheduled work includes: Miller Road Bridge: Continue framing the bridge deck for Miller Road Ground Improvements: Continue to drive timber piles south of Miller Road Continue installation of pile caps and load transfer platform Woods Creek Bridge: Installation of cofferdams to isolate bridge construction from Woods[...]