The week of 11/17/2025, scheduled work includes: Miller Road Bridge: Preparation work for bridge approach slabs Ground Improvements: Continue to[...]
Stage 2
Randall Road Project Update
The week of 11/10/2025, scheduled work includes: Miller Road Bridge: Curing period for new bridge deck Preparation work for bridge[...]
Randall Road Project Update
The week of 11/03/2025, scheduled work includes: Miller Road Bridge: Continue framing and setting reinforcing steel on the bridge deck[...]
Project Update: Miller Road Bridge Progress
Work on the Miller Road Bridge and Randall Road intersection is progressing. The project team will be taking advantage of[...]
Randall Road Project Updates
The week of 10/20/2025, scheduled work includes: Miller Road Bridge: Continue framing the bridge deck for Miller Road. Ground Improvements:[...]
Randall Road Project Update
The week of 10/13/2025, scheduled work includes: Miller Road Bridge: Install river rock in channel under Miller Bridge Begin framing[...]
Randall Road Project Update
The week of 10/06/2025, scheduled work includes: Miller Road Bridge: Frame and pour the south half of the east abutment[...]
Randall Road Project Update
The week of 9/29/2025, scheduled work includes: Miller Road Bridge: Frame and pour the south half of the east abutment[...]
Randall Road Project Update
The week of 9/22/2025, scheduled work includes: Miller Road Bridge: Frame and pour the south half of west abutment Fill[...]
Randall Road Project Update
The week of 9/15/2025, utility relocation work is nearing completion. Scheduled work on the Miller Road bridge includes: Pouring the[...]