The week of 10/06/2025, scheduled work includes: Miller Road Bridge: Frame and pour the south half of the east abutment[...]
Stage 2
Randall Road Project Update
The week of 9/29/2025, scheduled work includes: Miller Road Bridge: Frame and pour the south half of the east abutment[...]
Randall Road Project Update
The week of 9/22/2025, scheduled work includes: Miller Road Bridge: Frame and pour the south half of west abutment Fill[...]
Randall Road Project Update
The week of 9/15/2025, utility relocation work is nearing completion. Scheduled work on the Miller Road bridge includes: Pouring the[...]
Randall Road Project Update
The week of 9/8/2025, crews will remain active along Randall Road and Miller Road with continued utility relocation efforts. Work[...]
Randall Road Project Update
The week of 9/1/2025, multiple operations will continue along Randall Road and Miller Road, including ongoing utility relocation work. Pile[...]
Randall Road Project Update
The week of 8/25/2025, multiple operations will continue along Randall Road and Miller Road, including ongoing utility relocation work. Pile[...]
Miller Road West Leg Closure Now in Effect
As of Monday, July 14, the west leg of Miller Road at Randall Road is officially closed as part of[...]
Randall Road Project Update and Upcoming Detour
The week of 7/14/2025, utility relocation work is progressing and will continue along Randall Road. The detour for the closure[...]
Randall Road Project Update and Upcoming Detour
The week of 7/7/2025, utility relocation work is progressing and will continue along Randall Road in preparation for the upcoming[...]