Excavation and stone placement for the temporary pavement continues along the east side of Randall Road. Excavation for the northbound retaining wall continues between Harnish Drive and Huntington Drive. Storm sewer installation has begun as well.  Next week, earth excavation and stone placement will continue, and storm sewer installation and piling installation at the retaining wall will begin.  All work is weather dependent. 

Please drive carefully through the construction zone.