Tree and brush removal continues along the east side of Randall Rd., north of Harnish Dr. to Huntington Dr. Once the area is cleared of trees and brush, the contractor will begin excavation to get ready for the new retaining wall installation.
Utility relocation will continue with Com Ed working along Algonquin Rd., Nicor working along Randall Rd. and Algonquin Rd., and ATT working on Randall Rd. north of Harnish Dr.
Project work is dependent on the weather. Please use caution when traveling through the work zone.