Beginning the week of September 24, 2018, installation of temporary traffic signals and temporary lighting will begin at various intersections.  This ongoing work will continue for the next month as crews prepare to remove the existing systems to allow the staging of traffic for reconstruction.  Most work will be completed behind the curb, but periodic flagging operations and lane closures should be expected.

Also, the week of September 24, 2018, Nicor Gas will begin utility relocation work along the north side (westbound lanes) of Algonquin Road.  Work will be completed behind the curb, but periodic flagging operations and occasional lane closures should be expected.  Traffic disruptions may occur, expect delays.

Electronic signs have been installed throughout the project route to relay up-to-date project information.

As always, please travel through the area with caution, pay attention to workers, and check the website www.randallroad.info for more information on the improvements.