Update: Week of 11/9/2026

Traffic Alerts:

  • The left turn lanes to and from Alexandra Boulevard are expected to reopen November 16, following the installation of the new intersection pavement.
  • The week of November 16, northbound Randall Road traffic will be shifted from the existing pavement to the new pavement from north of Miller Road to Ackman Road.

This week, work continues on the Randall Road Improvements project, with multiple construction activities underway simultaneously. Upcoming activities include:

Randall Road:

  • Pour permanent pavement at Alexandra intersection, pour select southbound left-turn lanes.
  • Install temporary asphalt pavement to accommodate northbound traffic.
  • Begin installing ground improvement wood piling in center lanes starting at Miller Road and progressing south.
  • East Side of Randall: Complete tree removal along the east side of Randall Road, south of Miller Road, in preparation for roadway widening and retaining wall construction.

Bridge Work: Form and pour remaining piers on the east half of Woods Creek Bridge.

Drivers should use caution, allow additional travel time, and follow posted signs and traffic control devices in the area.