Update: Week of 10/05/2026

This week, work continues on the Randall Road Improvements project, with multiple operations occurring simultaneously. Upcoming construction activities include:

  • Miller Intersection: Crews will complete aggregate base and preparation for concrete paving. Early week of 10/5/26 the concrete pavement placement will start to connect the area of Randall Road at Miller Road.
  • Miller Road west leg: Parkway work behind the curbs will start, preparing for sidewalk installation and restoration.
  • Bridge Work: Construction of the second half of Woods Creek continues with driving test piles, completing the demolition of the existing triple cell box culvert and beginning removal of the existing sight screen/retaining wall.
  • Retaining Wall Work: Painting of new retaining walls is ongoing.

Traffic Alert:
The Miller Road West Leg Closure Continues
The west leg of Miller Road at Randall Road remains closed. Recent rain has delayed work, and the reopening is now anticipated for late October. We will provide an updated timeline as work progresses.

During this closure, a detour route is in place. Drivers should follow posted detour signs:

🔁 Detour Route:

➡️ From the north on Randall – Use Ackman Rd west to  → Lakewood Rd south

🔁 Alternate Route:

⬅️ From the south on Randall – Use Algonquin Rd west → to Lakewood Rd north

📍 Click here for a Detour Map
🎥 Click here to watch Detour Route Video

Please Note: Bradford Lane between Miller Road and Ashford Lane will be closed by the City of Crystal Lake while the Miller Road detour is in place.

Drivers are encouraged to plan ahead, allow additional travel time, and use the designated detour route when traveling through the area.