Update – Week of 6/29/2026
There will be no construction work from Friday, July 3 through Sunday, July 5 due to the 4th of July holiday weekend and the United States’ 250th Anniversary.
We wish everyone a safe and happy 4th of July holiday weekend!

Traffic Alert:
Alexandra Boulevard closed on June 1st at Randall Road to allow for intersection reconstruction.

  • This is an intersection-only closure — Alexandra Boulevard will remain open outside of Randall Road.
  • Access to and from Randall Road will remain available via Miller Road and Village Road for key left-turn movements. Angela Lane will remain open for right-turn movements.
  • Closure durations and schedules remain weather dependent and may shift as work progresses.
  • Work is progressing on Alexandra Boulevard. Base stone has been placed with top layer to be installed and graded next week. Tentative concrete pour week of June 29th.

This week work continues on the Randall Road Improvements project, with multiple operations occurring simultaneously. Upcoming construction activities include:

  • Continued excavation, earthwork and stone base operations from Alexandra Boulevard to Ackman and from Woods Creek bridge to the south limits
  • Fill placement from Miller Road to the south project limits
  • Stone base placement from Miller Road to the south project limits
  • Sidewalk prep and pour Village Road to Angela Lane
  • Bridge parapet forming at Woods Creek bridge
    • Continued retaining wall installation and backfilling
    • Continued topping work on newly installed retaining walls
  • Retaining wall work at Miller Road bridge

Expect frequent southbound lane closures through the work zone while crews work.