Traffic Alert:
Alexandra Boulevard closed on June 1st at Randall Road to allow for intersection reconstruction.
- This closure is expected to last approximately four weeks, weather permitting.
- This is an intersection-only closure — Alexandra Boulevard will remain open outside of Randall Road.
- Access to and from Randall Road will remain available via Miller Road and Village Road for key left-turn movements. Angela Lane will remain open for right-turn movements.
- Closure durations and schedules remain weather dependent and may shift as work progresses.
- Work is progressing on Alexandra Boulevard. Base stone has been placed with top layer to be installed and graded next week. Tentative concrete pour week of June 29th.
This week work continues on the Randall Road Improvements project, with multiple operations occurring simultaneously. Upcoming construction activities include:
- Continued excavation, earthwork and stone base operations from Alexandra Boulevard to Ackman
- Fill placement from Miller Road to the south project limits
- Stone base placement from Miller Road to the south project limits
- Sidewalk grading and prep work Village Road to Angela Lane
- Bridge parapet forming at Woods Creek bridge
- Continued retaining wall installation and backfilling
- Continued topping work on newly installed retaining walls
- Retaining wall work at Miller Road bridge
Expect frequent southbound lane closures through the work zone while crews work.
At times, only one southbound through lane on Randall Road will remain open.