The week of 12/08/2025, scheduled work includes:

Miller Road Bridge:

  • Continue pavement work adjacent to the bridge

Ground Improvements:

  • Continue installation of pile caps and load transfer platform

Woods Creek Bridge:

  • Installation of rebar, forming, and pouring piers

Roadway Work:

  • Miller Road backfill of newly poured curb
  • Miller Road and Randall Road intersection fill and grading of roadway

The detour for the closure of the west leg of Miller Road at Randall Road remains in effect. Traffic in the area continues to be observed, and changes will be made if necessary. Please follow the marked detour routes and use extra caution by observing speed limits through the detour and construction zone. Watch for upcoming information on timing for when this detour will be temporarily lifted and Miller Road reopened at Randall Road (early December, pending weather).