The week of 11/17/2025, scheduled work includes:

Miller Road Bridge:

  • Preparation work for bridge approach slabs

Ground Improvements:

  • Continue to drive timber piles south of Miller Road
  • Continue installation of pile caps and load transfer platform

Retaining Walls:

  • Installation of precast panels, Woods Creek to Miller Road
  • Installation of temporary wall, Woods Creek to Miller Road

Woods Creek Bridge:

  • Installation of rebar for piers, forming the piers

Roadway Work:

  • Excavation and grading, Angela Lane to Alexandra Boulevard
  • Miller Road grading and stone placement west of the bridge
  • Miller Road preparation for curb installation west of the bridge

The detour for the closure of the west leg of Miller Road at Randall Road remains in effect. Traffic in the area continues to be observed, and changes will be made if necessary. Please follow the marked detour routes and use extra caution by observing speed limits through the detour and construction zone. Watch for upcoming information on timing for when this detour will be temporarily lifted and Miller Road reopened at Randall Road (early December, pending weather).

📍 Click here for a Detour Map
🎥Click here for a Video showing the Detour Routes

Thank you for your continued patience during construction.