The week of 11/03/2025, scheduled work includes:
Miller Road Bridge:
- Continue framing and setting reinforcing steel on the bridge deck for Miller Road
Ground Improvements:
- Continue to drive timber piles south of Miller Road
- Continue installation of pile caps and load transfer platform
Woods Creek Bridge:
- Installation of the piling for the piers to begin
Roadway Work:
- Excavation and grading, Village Road to Angela
- Storm sewer installation from Village Road to Ackman
The detour for the closure of the west leg of Miller Road at Randall Road remains in effect. Traffic in the area continues to be observed, and changes will be made if necessary. Please follow the marked detour routes and use extra caution by observing speed limits through the detour and construction zone. Watch for upcoming information on timing for when this detour will be temporarily lifted and Miller Road reopened at Randall Road (early December, pending weather).
📍 Click here for a Detour Map
🎥Click here for a Video showing the Detour Routes
Thank you for your continued patience during construction.