The week of 9/29/2025, scheduled work includes:
Miller Road Bridge:
- Frame and pour the south half of the east abutment
Ground Improvements:
- Drive timber piles south of Miller Road
Roadway Work:
- Excavation, north of Woods Creek to Miller Road
- Excavation from Village Road to Angela Lane
- Storm sewer installation from Village Road to Angela Lane
- Utility relocation continues
Traffic Alert – Village Road at Randall Road Intermittent Closures
Village Road will be closed intermittently at Randall Road on Monday, September 29th, through Wednesday, October 1st, 2025, for construction. Closures will only affect Village Road traffic at the intersection — Randall Road will remain open in both directions.
Traffic Alert – City of Crystal Lake – Bradford Lane at Miller Road Closure
To reduce cut-through traffic from the Miller Road closure, the City of Crystal Lake is closing Bradford Lane at Miller Road while maintaining resident access from Village Road. This closure is tentatively scheduled to begin on 9/30/2025 and will remain in place while the Miller Road closure and detour is in effect. For questions, please email construction@crystallake.org or call 815-356-3605.
📍 Click here for a Map of the Bradford Lane Closure
The detour for the closure of the west leg of Miller Road at Randall Road is still in place. Traffic conditions in the area are being monitored, and adjustments will be considered as needed. We encourage drivers to follow the posted detour routes and pay close attention to speed limits throughout the detour route and around the construction zone.
📍 Click here for a Detour Map