The week of 9/8/2025, crews will remain active along Randall Road and Miller Road with continued utility relocation efforts. Work on the new Miller Road bridge also progresses, with pile driving and abutment construction moving forward. Roadway excavation and aggregate base installation are advancing north toward Village Road.

The detour for the closure of the west leg of Miller Road at Randall Road remains in effect. Traffic in the area continues to be observed, and changes will be made if necessary. Please follow the marked detour routes and use extra caution by observing speed limits through the detour and construction zone.

📍 Click here for a Detour Map
🎥 Click here for a Video showing the Detour Routes

Thank you for your continued patience during construction.