🚧 The detour for the closure of the west leg of Miller Road at Randall Road is now in effect to allow for bridge construction. Traffic conditions in the area are being monitored, and adjustments will be considered as needed in coordination with project partners. We encourage drivers to follow the posted detour routes around the construction zone. Drivers are advised to plan and allow extra time when traveling through the area.

With the Miller Road closure now in place, the contractor is moving forward with key roadway and bridge improvements in the area. The week of 7/21/2025, multiple operations will continue along Randall Road and Miller Road, including ongoing utility relocation work. Ground improvements are scheduled to begin, with pile driving operations and preliminary work on the new Miller Road bridge getting underway. Storm sewer installations and roadway excavation will also be in progress.

Thank you for your continued patience during construction.

📍 Click here for a Detour Map
🎥 Click here for a Video showing the Detour Routes