Work completed last week:
Randall Road:
- Poured miscellaneous curb, gutter and sidewalk gaps
- Completed storm sewer on Acorn Lane
- Filled in intersection pavement panels on Acorn and at drives
- Placed topsoil, grass seed and erosion control blanket
- Completed pouring all sections of the sidewalk and crash wall on the north bound retaining wall
- Installed lighting and signal foundations along northbound Randall Road
Algonquin Road:
- Completed landscaping on Algonquin Rd.
Work coming up:
The winter season is upon us and this precludes a majority of the work that can be done. Electrical items will continue to
be worked on as weather permits. All other work is suspended until Spring 2021.
Randall Road:
- Installation of street lighting and traffic signal conduits and foundations
Algonquin Road:
- No work until spring 2021