Update: Week of 11/16/2026

Traffic Alerts:

  • The left turn lanes to and from Alexandra Boulevard are expected to reopen November 17, following the installation of the new intersection pavement.
  • Tuesday, November 17, northbound Randall Road traffic will be shifted from the existing pavement to the new pavement from north of Miller Road to Ackman Road.

This week, work continues on the Randall Road Improvements project, with multiple construction activities underway simultaneously. Upcoming activities include:

  • Randall Road:
    • Excavation for timber pile ground improvement system.
    • Begin installation of timber pile ground improvement in center lanes starting at Miller Road and progressing south.
    • Excavation and grading for new sidewalk, Acorn Lane to Woods Creek.
    • Continue installing new traffic signal equipment at the intersections of Miller Road and Alexandra Boulevard.
    • Removal of the existing east fence from Miller Road to Angela Lane.
  • Bridge Work at Woods Creek:
    • Excavation for the south abutment and MSE Wall.
    • Drive south abutment piles.
    • Begin MSE Wall installation at south abutment.
    • Frame and pour north pier cap.

Drivers should use caution, allow additional travel time, and follow posted signs and traffic control devices in the area.

Comments are disabled