Update: Week of 8/10/2026
This week, work continues on the Randall Road Improvements project, with multiple operations occurring simultaneously. Upcoming construction activities include:

  • Sidewalk prep and installation at various locations along Randall Road
  • Roadway parapet forming and concrete pours north and south of the Woods Creek bridge
    • Continued topping work on newly installed retaining walls
    • Staining of the concrete walls along the bridge
  • Retaining wall work at Miller Road bridge
  • Installation of temporary sheeting at Miller Road for existing removals
  • Installation of street lighting infrastructure

Expect frequent southbound lane closures through the work zone while crews work.

Traffic Alert: The Miller Road West Leg Closure is in Effect

The west leg of Miller Road at Randall Road is now closed. The closure is expected to remain in place for approximately 8 to 10 weeks.

During this closure, a detour route will be in place. Drivers should follow posted detour signs:

🔁 Detour Route:

➡️ From the north on Randall – Use Ackman Rd west to  → Lakewood Rd south

🔁 Alternate Route:

⬅️ From the south on Randall – Use Algonquin Rd west → to Lakewood Rd north

📍 Click here for a Detour Map
🎥 Click here to watch Detour Route Video


Please note:
Bradford Lane between Miller Road and Ashford Lane will be closed by the City of Crystal Lake while the Miller Road detour is in place.

Drivers are encouraged to plan ahead, allow additional travel time, and use the designated detour route when traveling through the area.

Thank you for your continued patience during the construction.