Update – Week of 7/13/2026

Traffic Alert:
Alexandra Boulevard closed at Randall Road to allow for intersection reconstruction.

  • This is an intersection-only closure — Alexandra Boulevard will remain open outside of Randall Road.
  • Access to and from Randall Road will remain available via Miller Road and Village Road for key left-turn movements. Angela Lane will remain open for right-turn movements.
  • Closure durations and schedules remain weather dependent and may shift as work progresses.
  • Work is progressing on Alexandra Boulevard. Base stone has been placed and graded. Concrete pour week of July 13.

This week work continues on the Randall Road Improvements project, with multiple operations occurring simultaneously. Upcoming construction activities include:

  • Continued excavation, earthwork, and stone base operations from the south project limits through the Woods Creek Bridge to Miller Road
  • Pavement preparation and concrete pours from south of Alexandra Boulevard to the north project limits
  • Preparation and concrete pours for intersection improvements at Alexandra Boulevard
  • Pavement preparation and concrete pours from the south project limits (Acorn/Polaris) to Woods Creek Bridge
  • Sidewalk preparation and concrete pours from Village Road to Angela Lane
  • Bridge and roadway parapet forming and concrete pours at the Woods Creek bridge
    • Continued retaining wall installation and backfilling
    • Continued topping work on newly installed retaining walls
    • Staining of the concrete walls along the bridge
  • Retaining wall work at Miller Road bridge

Expect frequent southbound lane closures through the work zone while crews work.