Update – Week of 3/30/2026
Construction activities will focus on the area north and south of the Woods Creek Bridge and may include:
- Continued installation and backfilling of retaining walls
- Ongoing construction of the bridge structure
- Installation of the creek bed stabilization
- Continued topping work on the retaining walls already in place
Traffic: Expect frequent southbound lane closures at the bridge while crews work, with only one southbound through lane open on Randall Road at times.
