Update – Week of 3/9/2026
Crews will be working as weather permits. Work will focus on the Woods Creek Bridge and may include:
- Continued installation and backfilling of retaining walls
- Ongoing construction of the bridge structure
- Installation of the creek bed stabilization
- Begin the work on the topping of the retaining walls already in place
Traffic: Expect frequent southbound lane closures at the bridge while crews work, with only one southbound through lane open on Randall Road at times.
