Happy New Year! During the upcoming week of 1/12/2026, crews will be working as weather permits.

Scheduled work, weather permitting, includes:


Miller Road Bridge:

  • Continue work adjacent to the bridge on walls and grading.


Ground Improvements:

  • Continue installation of load transfer platform for the roadway base.


Woods Creek Bridge:

  • Continue with the installation of retaining walls and building of the structure.


Roadway Work: No work planned


The detour for the west leg closure of Miller Road at Randall Road was lifted on
Friday, December 12th. Traffic is now flowing freely through the intersection.