Happy New Year! During the upcoming week of 1/12/2026, crews will be working as weather permits.
Scheduled work, weather permitting, includes:
Miller Road Bridge:
- Continue work adjacent to the bridge on walls and grading.
Ground Improvements:
- Continue installation of load transfer platform for the roadway base.
Woods Creek Bridge:
- Continue with the installation of retaining walls and building of the structure.
Roadway Work: No work planned
The detour for the west leg closure of Miller Road at Randall Road was lifted on Friday, December 12th. Traffic is now flowing freely through the intersection.