During the upcoming weeks of 12/22/2025 and 12/29/2025, crews will be working as weather permits and will be off intermittently in observance of the holidays.

Scheduled work, weather permitting, includes:

Miller Road Bridge:

  • Continue work adjacent to the bridge

Ground Improvements:

  • Continue installation of pile caps and load transfer platform

Woods Creek Bridge:

  • Continue with the installation of rebar, forming, and pouring of piers; excavation for abutments; pile driving; removal of cofferdams; and the installation of retaining walls.

Roadway Work: No work planned

The detour for the west leg closure of Miller Road at Randall Road was lifted on Friday, December 12th. Traffic is now flowing freely through the intersection.

The entire Randall Road Improvements team wishes you a very happy holiday season!