The week of 11/24/2025, scheduled work includes:
Miller Road Bridge:
- Continue pavement work adjacent to the bridge
Ground Improvements:
- Continue to drive timber piles south of Miller Road
- Continue installation of pile caps and load transfer platform
Retaining Walls:
- Installation of precast panels
Woods Creek Bridge:
- Installation of rebar, forming, and pouring piers
- Set and backfill precast panels at bridge approaches
Roadway Work:
- Preparation for winterization of Angela Lane and Village Road
- Miller Road backfill of newly poured curb
- Miller Road and Randall Road intersection fill and grading of roadway
The detour for the closure of the west leg of Miller Road at Randall Road remains in effect. Traffic in the area continues to be observed, and changes will be made if necessary. Please follow the marked detour routes and use extra caution by observing speed limits through the detour and construction zone. Watch for upcoming information on timing for when this detour will be temporarily lifted and Miller Road reopened at Randall Road (early December, pending weather).
📍 Click here for a Detour Map
🎥Click here for a Video showing the Detour Routes
Thank you for your continued patience during construction.