The week of 10/06/2025, scheduled work includes:

Miller Road Bridge:

  • Frame and pour the south half of the east abutment
  • Frame retaining walls at bridge

Ground Improvements:

  • Continue to drive timber piles south of Miller Road

Roadway Work:

  • Excavation, stone placement and grading, Miller Road to Village and South of Woods Creek
  • Storm sewer installation from Village Road to Angela Lane
  • Utility relocation continues

Traffic Alert – Village Road at Randall Road and Angela Lane at Randall Road Intermittent Closures
Village Road and Angela Lane will be under flagging conditions at times for construction and underground installation activities. Flaggers will assist traffic through the intersections when work is impacting — Randall Road will remain open in both directions.

Traffic Alert – City of Crystal Lake – Bradford Lane at Miller Road Closure
To reduce cut-through traffic from the Miller Road closure, the City of Crystal Lake closed Bradford Lane at Miller Road while maintaining resident access from Village Road. This closure began on 9/30/2025 and will remain in place while the Miller Road closure and detour is in effect.  Emergency Services for the two communities have been notified and have contingency plans in place. For questions, please email construction@crystallake.org or call 815-356-3605.

📍 Click here for a Map of the Bradford Lane Closure

The detour for the closure of the west leg of Miller Road at Randall Road is still in place. Traffic conditions in the area are being monitored, and adjustments will be considered as needed. We encourage drivers to follow the posted detour routes and pay close attention to speed limits throughout the detour route and around the construction zone.

📍 Click here for a Detour Map
🎥Click here for a Video showing the Detour Routes