The week of 9/15/2025, utility relocation work is nearing completion. Scheduled work on the Miller Road bridge includes:
-
Pouring the north half of the east abutment
-
Excavation and pile driving for the south half of the east and west abutments
-
Driving piles for the southwest sheet pile retaining wall
Additional activity includes continued excavation for the timber pile ground improvement system south of Miller Road. Later in the week, excavation north of Village Road is scheduled to begin.
The detour for the closure of the west leg of Miller Road at Randall Road remains in effect. Traffic in the area continues to be observed, and changes will be made if necessary. Please follow the marked detour routes and use extra caution by observing speed limits through the detour and construction zone.
📍 Click here for a Detour Map
🎥 Click here for a Video showing the Detour Routes
Thank you for your continued patience during construction.