The week of 9/1/2025, multiple operations will continue along Randall Road and Miller Road, including ongoing utility relocation work. Pile driving and bridge abutment construction continues for the new Miller Road bridge. Roadway excavation and aggregate base placement continues north toward Village Road.

The detour for the closure of the west leg of Miller Road at Randall Road is still in place. Traffic conditions in the area are being monitored, and adjustments will be considered as needed. We encourage drivers to follow the posted detour routes and pay close attention to speed limits throughout the detour route and around the construction zone.

📍 Click here for a Detour Map
🎥Click here for a Video showing the Detour Routes

Wishing everyone a safe and happy Labor Day weekend—please drive carefully! 🚗

 