Signal Activation Update
A new temporary signal at Alexandra Blvd. and Randall Rd. is scheduled to be activated the week of 4/7/25. This signal will become a permanent part of the Randall Road improvements, providing full protected access to and from Alexandra in all directions.
Upcoming Construction
The week of 4/7/25, the contractor will be filling in the recently removed medians from north of Acorn Ln./Polaris Dr. to Ackman Rd. to prepare for temporary pavement. Work on the parkways will begin with the removal and stockpiling (for reuse later) of the topsoil in preparation of temporary pavement installation. Temporary lane closures may be in place during construction.
Join Us for an Open House
You’re invited to attend the Project Open House for details on the improvements, construction impacts, detours, and closures.
📅 Date: Tuesday, April 29th, 2025
⏰ Time: 5:00 PM – 7:00 PM
📍 Location: Lake in the Hills Village Hall
600 Harvest Gate Rd, Lake in the Hills, IL 60156