Work completed last week:

Randall Road:

  • Poured miscellaneous curb, gutter and sidewalk gaps
  • Completed storm sewer on Acorn Lane
  • Filled in intersection pavement panels on Acorn and at drives
  • Placed topsoil, grass seed and erosion control blanket
  • Completed pouring all sections of the sidewalk and crash wall on the north bound retaining wall
  • Installed lighting and signal foundations along northbound Randall Road

Algonquin Road:

  • Completed landscaping on Algonquin Rd.

 

Work coming up:

The winter season is upon us and this precludes a majority of the work that can be done. Electrical items will continue to

be worked on as weather permits.  All other work is suspended until Spring 2021.

Randall Road:

  • Installation of street lighting and traffic signal conduits and foundations

Algonquin Road:

  • No work until spring 2021