Work completed last week:
Check out this 30 day Glimpse into lane expansion work on Randall CLICK HERE.
Randall Road:
- Switched northbound Randall Road to the new pavement from Harnish to Huntington/Bunker Hill.
- Poured two new additional northbound concrete pavement lanes from Stonegate to Polaris, providing four travel lanes for the future roadway
- Completed concrete infill at the Randall Rd and Algonquin Rd intersection in anticipation of switching westbound Algonquin Rd onto the new proposed lanes.
- Continued electrical work on foundations and wiring for the street lights and traffic signals at various locations
- Completed installation of the railing on the southbound retaining wall for pedestrian safety
- Resumed work on the northbound retaining wall
Algonquin Road:
- Completed Crystal Lake Road and various other driveways on the north side of Algonquin in anticipation of the traffic switch
- Landscaping on the north side of Algonquin
- Continued median installations
- Switched westbound Algonquin Rd traffic onto the newly constructed concrete pavement. This traffic will remain in the proposed lanes through project completion
Work coming up:
Randall Road:
- Continued work on various side streets
- Curb/stone base installation on Stonegate, Huntington and Bunker Hill
- Various driveway construction
- Water main construction at Huntington
- Railing installation near the pedestrian underpass
- Continued work on northbound retaining wall
- Installation of the remaining retaining wall at the east entrance to the pedestrian tunnel
- Earth/concrete removal to be reused as the base for the new roadway between Harnish and Huntington
- Storm sewer work
- Concrete pavement installation for turn lanes and gaps from Stonegate to the north end of the project
- Asphalt installation on Acorn and other side streets
Algonquin Road:
- Continued landscaping
- Miscellaneous concrete sidewalk and curbs installation
- Median installation
- Work on various side streets and driveways