Work completed last week:

Randall Rd

  • Concrete temporary pavement placement for the remainder of section south of Bunker Hill Dr. was completed
  • Worked on sidewalk preparation/placement and landscaping between Bunker Hill Dr. and Algonquin Rd.
  • Continued pavement removal on the east side of Randall Rd from the project north limit to Stonegate Rd.
  • Installed traffic signal and street lighting foundations
  • Completed pouring retaining walls at the pedestrian underpass. CLICK HERE to View Video of The Underpass and Boardwalk.
  • Working on the pavement and barrier wall along the roadway retaining wall south of Bunker Hill Dr.
  • Worked on excavation and stone placement south of Algonquin Rd.

Algonquin Rd

  • Continued placing concrete pavement sections at driveways/side streets, installed curb and medians
  • Installed asphalt driveways and patching on Algonquin Rd.
  • Installed street lighting components on the north side of Algonquin Rd.

Side streets

  • Continued work on various side streets – excavation, stone and pavement placement

Upcoming work:

Randall Rd

  • Continue forming and pouring crash wall on the Southbound retaining wall
  • Installation of remaining concrete items and hand rails at the west side pedestrian underpass
  • Topsoil installation at pedestrian underpass
  • Form and pour sidewalk – Harnish Rd. to Bunker Hill Dr.
  • Continue installation of traffic signal and street light items – Harnish Rd. to Bunker Hill Dr.
  • Storm sewer installation will continue Algonquin Rd to Acorn Lane
  • Earth excavation and stone base placement to follow storm sewer completion

Algonquin Rd:

  • Prep and pour sidewalks
  • Work on curb and gutter, median and driveway installation.
  • Install infrastructure for street lights and traffic signals

Side streets: continue work on various side streets