Work completed last week

Randall Rd:

  • Asphalt placement continued at various locations including driveways
  • Miscellaneous concrete pours occurred for driveways and turn lanes
  • Huntington Dr., Bunker Hill Dr. and Polaris Dr. excavated and storm sewer and stone placed
  • Pavement removal was completed in the southbound lanes from Bunker Hill Dr. to Harnish Dr. and
    storm sewer installation began in this area
  • Work proceeded on the walls of the pedestrian underpass on the west side of the road 
  • Street lights were installed from Bunker Hill Dr. to Algonquin Rd
  • Work continued on various traffic signals

Algonquin Rd:

  • Excavation/stone placement continued on the Algonquin Rd. storm sewer

Upcoming work:

Randall Rd:

  • Storm sewer installation will continue in the area from Bunker Hill Dr. to Harnish Dr., and at the pedestrian underpass.
  • Excavation and stone base placement will continue from Bunker Hill Dr. to Harnish Dr.
  • Concrete pours of remaining curb, pavement and miscellaneous items from Bunker Hill Dr. to the north will be placed
  • Electrical work and foundations for the traffic signals and street lighting will continue
  • Sidewalk preparations and pouring is scheduled
  • Topsoil placement will occur in the next 1-2 weeks
  • Excavation and installation of the west half of the pedestrian underpass will occur

Algonquin Rd:

  • Algonquin Rd stone base will be completed, concrete pour of the 2 westbound lanes will be during the week of 8/3 – expect delays and watch for truck and equipment traffic on pour days.