Work Last Week:

Randall Rd:

  • Installed asphalt driveways, widening and pavement at Polaris and Commercial Dr.
  • Excavated Huntington Rd to grade and placed stone base
  • Asphalt placement occurred on Polaris Dr. and Commercial Dr. Asphalt entrances were
    also installed
  • Street light installation continued along Randall Rd.
  • Work continued on the southbound retaining wall and the pedestrian underpass
  • Installation continued of piling for the path leading to the west side of the pedestrian tunnel

Algonquin Rd:

  • Storm sewer installation along Algonquin Rd continued

Upcoming Work:

Randall Rd:

  • Asphalt placement will continue at various locations including driveways and southbound widening of the road will occur at the north limit of the project
  • Miscellaneous concrete pours will occur to place gaps and drives
  • Huntington Dr., Bunker Hill Dr. and Polaris Dr. will have excavation, storm sewer and stone placement
  • Pavement removal in the southbound lanes at the wall will occur and the storm sewer will be installed in this area
  • Work will proceed on the walls of the pedestrian underpass on the west side 

Algonquin Rd:

  • Algonquin Road storm sewer and excavation/stone placement will continue