RECENT WORK COMPLETED:

Randall Road:

  • Storm sewer installation is complete from Bunker Hill Dr. to Stonegate Rd. 

Algonquin Road:

  • Concrete installation is complete on the south leg of the Algonquin Rd./Crystal Lake Rd. intersection.  The intersection has reopened to traffic.

 CLICK HERE to see photos.

WORK PLANNED FOR WEEK OF 5/11/2020:

Randall Road:

  • A large main line concrete installation is scheduled for Tuesday 5/12 from Algonquin Rd to north of Polaris Dr.  Miscellaneous smaller concrete pours are scheduled for the balance of the week.
  • Storm sewer work continues from Stonegate Rd. to Algonquin Rd.
  • Excavation is set to begin mid-week on the southbound retaining wall (Harnish Dr. to Bunker Hill Rd.) Pile driving to follow.

Algonquin Road:

  • Miscellaneous concrete installations are scheduled at the Randall Rd. intersection.
  • Street Lighting installation of conduit and pole bases is planned.