Work continues on the Randall Road Improvements.

Storm Sewer
Storm sewer installation is complete on Randall Rd. from Acorn Ln./Polaris Dr. to Bunker Hill Dr./Huntington Dr.  Remaining storm sewer installation on Randall Rd. from Bunker Hill Dr./Huntington Dr. to Harnish Dr. will resume in the spring. 

Pavement
Eastbound Algonquin Rd. from Harvest Gate to Crystal Lake Rd. and southbound Randall Rd. from Acorn Ln./Polaris Dr. to Algonquin Rd. has been prepared for permanent concrete pavement placement in the spring. 

Pedestrian Underpass
Construction work on the east side of the pedestrian underpass is ongoing.  CLICK HERE to see photos of the pedestrian underpass retaining wall being constructed.

Retaining Wall
Work will begin on the southbound retaining wall on Randall Rd. as weather permits.  

Have a Safe and Happy Holiday Season!